Timeline
| Milestones | Approximate Completion |
| Letters of Agency Signed | September 17 |
| Sign Up Survey Complete | September 17 |
| RFP Draft Complete | End of August |
| PFP Released to USAC | Early October |
| RFP Open to Bidders | Mid-October |
| First Bidder's Meeting | 15 days after release |
| Last Bidder's Meeting | 30 days before due |
| Bids Due | 75 days after release |
| Evaluation of Bids | Q1 2009 |
| Contract Signed | Q1 2009 |