Milestones Approximate Completion
Letters of Agency Signed September 17
Sign Up Survey Complete September 17
RFP Draft Complete End of August
PFP Released to USAC Early October
RFP Open to Bidders Mid-October
First Bidder's Meeting 15 days after release
Last Bidder's Meeting 30 days before due
Bids Due 75 days after release
Evaluation of Bids Q1 2009